Beaver Ave Construction
I highly recommend that you all avoid Beaver Ave the first few Saturdays or at least DON'T use the left lane!
Here is the full rundown from SC Boro
Here is the Beaver Water Line Update.
Completed Work
HRI has completed the installation of the new 12" water main on Beaver
Avenue. They also completed connecting all water service connections
and the existing mains on the side streets to the new 12" water main
early Thursday morning. This means that all installation work for the
new water main has been completed approximately 3 weeks ahead of
schedule.
Anticipated Work Schedule
August 25 - September 12
HRI will continue permanent restoration of the curbing and
roadway during daylight hours in the remaining blocks. They will be
working west on Beaver Avenue from Garner Street.